SLUUC27C June   2019  – July 2022 BQ25611D , BQ25619

 

  1.   BQ25611D, BQ25619 (BMS025) Evaluation Module
  2.   Trademarks
  3. 1Introduction
    1. 1.1 EVM Features
    2. 1.2 I/O Descriptions
  4. 2Test Summary
    1. 2.1 Equipment
    2. 2.2 Equipment Setup
    3. 2.3 Software Setup
    4. 2.4 Test Procedure
      1. 2.4.1 Initial Settings
      2. 2.4.2 Communication Verification
      3. 2.4.3 Charger Mode Verification
      4. 2.4.4 Boost Mode Verification
      5. 2.4.5 Evaluation Results
      6. 2.4.6 Helpful Tips
  5. 3PCB Layout Guideline
  6. 4Board Layout, Schematic, and Bill of Materials
    1. 4.1 Board Layout
    2. 4.2 Schematics
    3. 4.3 Bill of Materials
  7. 5Revision History

Boost Mode Verification

Use the following steps for boost mode verification:

  1. Turn off and disconnect PS1.
  2. Set Load #1 to 3.7V and 2A current limit.
    Note:

    If Load #1 connected from BATTERY-J4(3) to PGND-J4(1) is not a four quadrant supply, remove Load #1 and use PS1 (disconnected in 8.4.1), set to 3.7V, 2A current limit and connect to BATTERY-J4(3) to PGND-J4(1).

  3. In the EVM software, check GUID-948712F2-3122-4176-BAE9-A44CF6BB0A8E-low.gif.
  4. Connect Load #2
    • For BQ25619 (BMS025-005): across VPB-J3(1) and PGND-J3(2).
    • For all others: across VIN-J1(2) and PGND-J1(1).
    • For BQ25619, measure VPB (VPB-TP14 and PGND-TP32) = 5.0V ±0.2V.
    • For all others, measure VBUS (VBUS-TP12 and PGND-TP31) = 5.0V ±0.2V.
  5. Turn off and disconnect power supply.
  6. Remove Load #2 from connection.