SPNU615B April 2015 – January 2020 RM42L432 , RM44L520 , RM44L920 , RM46L430 , RM46L440 , RM46L450 , RM46L830 , RM46L840 , RM46L850 , RM46L852 , RM48L530 , RM48L540 , RM48L730 , RM48L740 , RM48L940 , RM48L950 , RM48L952 , RM57L843 , TMS570LC4357 , TMS570LC4357-EP , TMS570LC4357-SEP , TMS570LS0332 , TMS570LS0432 , TMS570LS0714 , TMS570LS0714-S , TMS570LS0914 , TMS570LS1114 , TMS570LS1115 , TMS570LS1224 , TMS570LS1225 , TMS570LS1227 , TMS570LS2124 , TMS570LS2125 , TMS570LS2134 , TMS570LS2135 , TMS570LS3134 , TMS570LS3135 , TMS570LS3137 , TMS570LS3137-EP
Add a new folder and type “MyTests” in the test folder created by the tool. Define the test sequence and save it in the folder “Test1” inside MyTests. Figure 18 shows a template of a test sequence. Add more test sequences by adding more folders in MyTests.
Folder structure as shown in Figure 19 must be followed strictly.
NOTE
Points to keep in mind while writing a test sequence:
Figure 20 and Figure 21 show a few examples of a test case.
Tip: Right-click on the test list field and click “Refresh” to regenerate the list.