TIDT332 May   2024

 

  1.   1
  2.   Description
  3.   Features
  4.   Applications
  5. 1Test Prerequisites
    1. 1.1 Voltage and Current Requirements
    2. 1.2 Required Equipment
    3. 1.3 Dimensions
    4. 1.4 Test Setup
      1. 1.4.1 Hardware Setup
      2. 1.4.2 Firmware Setup
      3. 1.4.3 Test Static Operation
      4. 1.4.4 Test Soft-Start Process
      5. 1.4.5 Test Voltage Balance Performance
      6. 1.4.6 Test Bidirectional Transition Process
  6. 2Testing and Results
    1. 2.1 Efficiency Graphs
    2. 2.2 Efficiency Data
    3. 2.3 Thermal Images
  7. 3Waveforms
    1. 3.1 Switching
    2. 3.2 Bidirectional Transient
    3. 3.3 Start-Up Sequence

Required Equipment

  • DC source 1: Chroma 62150H-1000S
  • DC source 2: IT6010C-80-300
  • Electronic load: Chroma 63203A-600-210

    (Note: Better to replace this E load with 1000V for full voltage test)

  • 12V DC source for control power: GPS-3303C
  • Oscilloscope: Tektronix, DPO 3054
  • Infrared Thermal Camera: Fluke, TiS60
  • Digital Power Meter: Yokogawa WT310
  • Software: Code Composer Studio™(CCS) and DigitalPower SDK
  • C2000 daughter card: TMDSCNCD280039C